SOCIAL FORESTRY DIVISION DASHBOARD
Kawasan Hutan Komunal Lubok Antu Samarahan
Proposed Design & Build for Commercial Agroforestry
information within hand.... Project Client : SOCIAL FORESTRY DIVISION
Scope of Works :
1. Infrastructure (roads, bridge, site office, clearing, etc);
2. Nursery and landscaping
3. Investors to come in for the own site finishing, planting and processing upon agreement with Koperasi and consent from Forest Department.
Date of Approval : 24.06.2019
Completion Date : 30.06.2021
Contract Sum : RM 5,000,000.00
Contractor : Koperasi Lubok Antu Reban Serian Bhd
Construction Period : 18 months
PEMULIHAN LANDSKAP HUTAN DENGAN CARA PERGKOMERSILAN HUTAN TANI DI SARAWAK
Job Progress Update October - December 2021
Work Progress (%)
Physical Progress Schedule vs Actual
No Data Found
Status Perbelanjaan (RM)
Jumlah Besar RM 2,798,265.77
No Data Found
Proposed Design & Built for Commercial Agroforestry
Lubok Antu CF - Project Chronology update to YAB CM
14/09/2018
Meeting chaired by YBhg. Permanent Secretary, MUDNeR to defer excision of LACF and instead agreed with the implementation of Commercial Agroforestry. He conveyed YAB CM concerned that once the CF is excised, the land would not be the locals due to lack of capital and capability, thus the easy way out is to sell the land.
27/09/2018
Stakeholders engagement Workshop to identify options for commercial agroforestry models
04/02/2019
2nd Engagement with YAB Chief Minister where he approved for the LACFAP Masterplan with a budget of RM 5 million to implement the project and the model for the future NCR development. He futher requested that the project site to the Pilot R&D for testing drone in forest plantation development. Refer to note by DDG to DF
13/05/2019
Presentation as Paper No. 33 to SDEC Meeting No 1/2019 chaired by YB State Secretary where the project was approved and endorsed.
24/06/2019
SPU conveyed Notice of Change NO 34/2019 to MUDeNR with the approved Project Cost RM5million. Ref: (118)JKM/SPU/602-5/1/15 Vol 3. as Projek Rakyat.
02/08/2020
Forest Department letter to KPLARSB requesting to submit procurement process with dateline till 30 August 2019
24/01/2020
FDS team led by DDF Jack Liam, LO Mohamad Mohaimin and Dawend Jiwan (Project Officer) meeting with SAG himself and his team. Decision made were: (i) to make amendment to Forest Ordinance, 2015 to insert agroforestry instead of domestic use inside Communal Forest and to include Carbon Offset project and definition; (ii) To proceed with issuance of Order to Koperasi Lubok Antu Reban Serian Bhd. After meeting YAB Chief Minister prior to tabling of Forest Ordinance amendment with terms and conditons. To study on the proposed joint venture agreement between KLASB and investors.
12/03/2020
Briefing to PSU MUDeNR on project status prior to SDMC MEeting
27/07/2020
Jawatankuasa Pemantauan Pembangunan Negeri (SDMC) Meeting at Wisma Bapa Malaysia directive to shorten the project implementation timeline from original schedule date from January 2020 till Dec 2021 to the revise project period from August 2020 till June 2021.
04/09/2020
Briefing and Dialogue Session with community and KLARSB members at Dewan Serbaguna Kpg. Lubok Ria Hulu.
26/10/2020
Memo Rasmi from SFS conveying Restropective Approval for Direct Award to KLARSB as Contractor.
31/10/2020
Dialogue and site visit by Director of Forests in attendance of locals, IADA, Serian dan Samarahan Resident representative and potential investor
12/11/2020
Contract no HQ/T/2020/04 signing for Project Rakyat Bil. 27/202 PEMULIHARAN LANDSKAP HUTAN DENGAN CARA PENGKOMERSILAN HUTAN-TANI DI SARAWAK: KAWASAN HUTAN KOMUNAL LUBOK ANTU SAMARAHAN.
25/11/2020
Director, IADA Samarahan and team project site visit and meeting at KARSB office.
04/12/2020
First payment made to KLARSB.
08/12/2020
Director, Suruhanjaya Koperasi Malaysia and team project site visit and meeting at KLARSB office.